After a brief conversation with the General Contractor I have an update on the pouring of concrete on the east side of the 300 block of N Washington. 1. There is a good chance that concrete will be poured starting tomorrow from the corner of E Burleson down to the Trophy store door. 2. Additional concrete will be poured starting on Thursday from the Trophy store south to just before the Radio Station 3. The remaining concrete to be poured on Friday most likely are the paver strip concrete as well as curb and gutter on the west side starting at E Burleson. Obviously this will effect certain store operation and hours once the concrete is poured as it needs at a minimum 24-hours before it can be walked on. This is good news as we all try to get this project moving forward. As always this schedule is weather and concrete plant dependent. Eric G. Powell, PE Director of Public Works & Utilities City Engineer 903-935-4489 City of Marshall PO Box 698 Marshall, TX 75671